To change the Evidence Type once the evidence has been assessed.
Note; We recommend the assessor performs these steps if the evidence have been verified because assessment feedback will need to be given at step 4.
1. Go to the evidence and click 'Assess'
2. Click 'Edit Evidence Properties'
3. Edit Evidence properties accordingly i.e. Plan, Type, and/or target date and click 'Save'
4. Click 'Cancel Assessment' , unless there is IQA feedback, in which case you will need to complete the assessment workflow again.
5. Go to the portfolio front page and click 'Check Completeness'
6. Click 'Check', then return to the portfolio front page and progress should be updated
Keywords: edit evidence type, amend evidence type, change evidence type, assessment complete, assessed evidence